Consultancy, Supervision and Project Management Consultancy

Overall Total
Total equivalent population (person) : 1000000
Total plant flow (m³/day) : 135000
Project: Consulting Services For The Construction Supervision For R2 Reservoir
Client :
Description of The Work :

The scope of works for the contract includes construction of:

  • Water storage reservoir with 135 ML water storage capacity and 163 m x 140 m x 6 m dimensions.
  • Overflow system
  • Pumping Station
  • Power transformers
  • Standbye power generation room
  • Fuel tanks building
  • Chlorination stationIrrigation pumping station
  • Valve chambers and connecting pipework
  • Pipework
  • Warehouse store
  • Guard house
  • Parking
  • Site roads and landscaping
  • Boundary roads and landscaping
  • Boundary roads and main gate
  • Residential building

The Supervision Phase of contract shall be divided in 3 phases/parts, as indicated below:

  • Pre-Construction Phase (Start Up Phase) – Before Construction
  • Construction Phase (Construction Phase) – During Construction
    • Task 1: Work Site Supervision
    • Task 2: Training and Capacity Building
  • Post-Construction Phase (Defect Liability Period)

 

Client:
Mayoralty of Baghdad

Date:
26.04.2022 / Ongoing​

Total Project Cost:
€ 1.326.328,76

test test test test test