Water Transmission Pipeline Projects

Overall Total
Length (km) : 494
Total plant flow (m³/day) : 1,379,206
Project Name
Length (km)
Total plant flow (m³/day)
Basmaya Residential Complex Water Supply Project in Baghdad Governorate
33
360,000
Client: Ministry of Municipalities and Public Works / Iraq <
Description of The Work: Basmaya is a new residential complex which is located in 25 km east of Baghdad. This city is planned to accommodate around 600.000 occupants in a total of 100.000 residential units. The scope of this project is to supply raw water for the city. This project consists of design, topographical surveyi...
Soma Thermic Power Plants, Cooling Water Supply Project (*)
28
85,000
Client: <
Description of The Work:

(*) Water transmission line projects managed and performed by ER-Ge's partners

Yataðan Thermic Power Plants, Cooling Water Supply Project (*)
12
85,000
Client: <
Description of The Work:

(*) Water transmission line projects managed and performed by ER-Ge's partners

Al-Ramadi Water Project in Anbar Governorate
55
240,000
Client: Ministry of Municipalities and Public Works / Iraq <
Description of The Work: Ramadi is the capital of Anbar Governorate and located in 110 km northwest of Baghdad with population of 427.301 in the goal year of 2038. The existing water treatment plant is insufficient to cover the potable water consumption of this city and especially for the new development areas in the west o...
Eskisehir Water Treatment Plant Extension and Water Transmission Line for Kalabak Spring Water Project
50
192,000
Client: <
Description of The Work: Water Treatment Plant Extension; Raw water is taken through the water intake structure and pumping station from the Porsuk River to the existing treatment plants of the city. The river is polluted with industrial wastes and agricultural materials carried by the stormwater. The existing water t...
Mardin Potable Water Group Project and Wastewater Treatment Plant
96
59,406
Client: Mardin Municipality / Turkey <
Description of The Work: Mardin Water Supply Group Project was originally started by the Iller Bank (Bank of Provinces) in 1985, and the design studies were approved in 1986. However, the design could not be implemented because of the lack of financial resource. Once the construction of Mardin Sewerage was started in 1997 a...
Design, Consulting and Construction Supervision Services of Erzurum Potable Water Transmission Line, Treatment Plant, Main Supply Lines and Water Storage Tanks Project
19
172,800
Client: Erzurum Metropolitan Municipality - Directorate of Water & Sewage / Turkey <
Description of The Work: Undertaking the complete engineering services including preparation of  a feasibility study, conceptual design, international tender documents in accordance with FIDIC procedures, technical specifications, assistance to the Employer for bidding and bid evaluation for the main transmission line ...
Supervision of the Construction 250 Boreholes Equipped with Hand Pumps & Design and Supervision of the Construction of Two Small Piped Systems in Three Districts of Gaza Province – Preparation Detailed Design for Two Small Piped System
30
-
Client: Ministry of Public Works, Housing & Water Resources - National Directorate of Water Supply & Sanitation / Mozambique <
Description of The Work: Supervision of drilling 250 Boreholes with average depth of 60 m in three districts of Gaza Province, including lining the borehole, filtering and borehole development, disinfection and flow test. Supervision of installation of hand pump for each borehole and concrete supporting deck. All the Superv...
Kadirli (Osmaniye) Water Supply System (Spring Water Catchment, Transmission Pipelines, Treatment Plant and Water Reservoirs)
19
35,000
Client: General Directorate of Bank of Provinces / Turkey <
Description of The Work: Kadirli  is a town and district of Osmaniye Province in the Mediterranean region of Turkey .The source of water for Kadirli is supplied from Kalealtı which is almost 22 km far from the city. The high amount of turbidity in source of Kalealtı was the major reason fo...
152
150,000
Client: <
Description of The Work: