Sewerage and Stormwater Network Design Works

Overall Total
Total plant flow (m³/day) : 13000
Length (km) : 172
Project: Samsun 19 Mayis Sewerage Network and Wastewater Treatment Plant and Deep Sea Outfall Preliminary Design
Client : General Directorate of Bank of Provinces / Turkey
Description of The Work :

The project covers preparation of the preliminary designs of sewerage network and treatment systems of Samsun “19 Mayıs” Town.

Plants will serve 65,000 people according to the population projections. The sewerage system covers the network and collector with a total length of 172 km. Wastewater biological treatment works consist of stabilization ponds and facultative aeration ponds. Length of the deep-sea outfall is 2,000 m.

 

The preliminary study report of the project was prepared, design criteria were defined, and the studies needed to establish an optimum sewerage system were carried out by considering the development plans and population distributions. Site studies were carried out upon approval of the first Study Report, and the preliminary designs of sewerage network and collector system and the biological treatment works and the deep-sea outfall.

 

CONSULTING SERVICES:

Services provided by ER-GE in this project:

  • Preparation of the First Project Study Report,
  • Preparation of necessary topographical studies,
  • Preparation of the preliminary designs for the sewerage system and collector,
  • Preparation of the preliminary designs for the biological wastewater treatment plant,
  • Preparation of the preliminary designs for deep sea outfall,
  • Preparation of quantities and cost estimations documents.

 

CLIENT: Provincial Bank General Directorate

DATE: 1992 - 1993

PROJECT COST: USD 20,000,000