Overall Total
Total plant flow (m³/day) : 360000
Length (km) : 33
Project: Basmaya Residential Complex Water Supply Project in Baghdad Governorate
Client : Ministry of Municipalities and Public Works / Iraq
Description of The Work :

Basmaya is a new residential complex which is located in 25 km east of Baghdad. This city is planned to accommodate around 600.000 occupants in a total of 100.000 residential units. The scope of this project is to supply raw water for the city.

This project consists of design, topographical surveying and geotechnical investigations. The source of water supply is Tigris River and project includes design of intake, screening units, raw water pumping stations and raw water transmission pipelines to the location of Water Treatment Plant within the city. The intake structure is trapezoidal concrete channel with depth of 16 m and length of 80 m. After intake there are coarse and fine screens, raw water reservoir and pumping station. Total length of raw water transmission pipelines is 2x16,5=33 km ductile iron with diameter of 1200mm and total flow of 15.000 m3/hr.

Services:

  • Preparation of Primary Report including different alternatives for raw water intake from Tigris and hydraulic alternatives of different  pipe diameters and pumping station and Technical & Financial Feasibility Report 
  • Preparation of EIA (Environmental Impact Assessment Report)
  • Undertaking topographical surveying for a route with total length of 16,5 km and width of 15 m for transmission pipeline and preparation contour elevation for 1,3 hectare land for raw water pumping station;
  • Undertaking in field soil borings test for total bore length of 75 m and 8 test pits along the route of transmission pipeline and preparation of Soil Investigation Report, including laboratory tests and bearing capacity of the soil in different depths
  • Preparation of detailed design of drawings including Plan-Profile, hydraulic calculation, detailed drawings of bends and connections, detailed design of 3 steel framed bridges with total length of 40 m passing above the creeks, detailed mechanical design of 250 mm Dual Air Valves, 300 mm Wash Out Valves and 1200 mm Butterfly Valves, structural design of Valve Chambers and detailed design of crossing under roads and creeks for total length of 33 KM Ductile Iron Pipes (K9) with diameter of 1200 mm for transmitting raw water from intake to Basmaya.
  • Preparation detailed design of trapezoidal intake channel with height of 16 m and width of 5 m in bottom and 36 m in top including structural design and special Slope Stability Report including Method of Statement and detailed technical specifications with total length of 83 m. Also preparation detailed design and Method of Statement for pipe jacking of dual 1500 mm steel spiral pipes with total length of 66 m under existing road between intake and raw water pumping station.
  • Preparation detailed design of pile foundation under screens units, water reservoir and pumping station structures.
  • Preparation Architectural, Mechanical, Electrical and Structural design of all components of the Raw Water Pumping Station including:
  • Fine and Coarse Screens
  • Water Reservoir
  • Raw Water Pumping Station
  • Flowmeter Room
  • Engineer and Operator Houses
  • Guard House
  • Operational Section
  • Potable Water Reservoir
  • Water Package Treatment
  • Road, fences, gates surrounding wall, landscape and lighting for the site
  • Fire water line, sewerage collection network, storm water collection network
  • Preparation Water Hammer calculation
  • Preparation of Final Design Report.
  • Preparation Technical Specifications, Slope Stability Report and Method of Statement.
  • Preparation Bill of Quantity for all the component of the work

 

Client:  Ministry of Municipalities and Public Works General Directorate of Water-Republic of Iraq

Date: 2013 – 2014

Total Service Cost: 325.000,00 USD